File #: 24-301    Version: 1 Name:
Type: Approval Item Status: Passed
File created: 7/10/2024 In control: CMAQ & TAP Project Selection Committee
On agenda: 7/18/2024 Final action: 7/18/2024
Title: Plainfield - 143rd Street from Wallin Drive to Van Dyke Road (12-24-0012)
Attachments: 1. 12-24-0012 CMAQ Transfer-Cost Increase Request

title

Plainfield - 143rd Street from Wallin Drive to Van Dyke Road (12-24-0012)

action

ACTION REQUESTED: Approval

purpose

PURPOSE & ACTION: The sponsor requests a transfer of $150,392 CMAQ from construction, with $16,000 to engineering 2, $80,000 to ROW, and $54,392 to construction engineering; a cost increase of $25,608 CMAQ for construction engineering in FFY 2026; and a schedule change to move engineering 2 from FFY 2024 to FFY 2025.

end