File #: 23-386    Version: 1 Name:
Type: Approval Item Status: Passed
File created: 8/23/2023 In control: CMAQ & TAP Project Selection Committee
On agenda: 8/31/2023 Final action: 8/31/2023
Title: Tinley Park- 84th Avenue and 179th St. Multi Use Path Extension (07-21-0006)
Attachments: 1. Tinley Park_TAP Cost Change Request
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Tinley Park- 84th Avenue and 179th St. Multi Use Path Extension (07-21-0006)

action

ACTION REQUESTED: Approval

purpose

PURPOSE & ACTION: The sponsor requests a cost increase of $156,800 TAP-L ($196,000 total) to cover increased wetland banking costs after an updated wetland delineation was performed.